The largest backlog in thirty years, and exactly two SMRs under construction

78 GW of nuclear capacity is under construction across 15 countries, one of the largest backlogs in thirty years, with ten construction starts totalling 12.2 GW in 2025, nine of them in China.

Against that, just two commercial small modular reactors are actually under construction anywhere: a 125 MW unit in China and a 300 MW unit in Russia.

Nuclear Construction & the SMR Reality Check

Data date
2025
Source class
Government / regulator
Data points
4
Sources
3
Value basis
4 actual

This page can answer

Two series: nuclear capacity under construction, and commercial SMR capacity actually being built.

It cannot answer

  • Completion dates, cost, or schedule performance.
  • Announced or planned SMRs, this counts construction only.
  • Operating fleet capacity or retirements.
Jump to chaptersSource ledger
Evidence chapters

Chapter 01 · Question answered

Nuclear capacity being built worldwide.

Nuclear capacity under construction

Under construction

Under construction

Reactor capacity being built worldwide, GW.

View data & sources →

Under construction

Rendering the interactive chart…

Expand data table
Download CSV
Nuclear capacity under construction: data table
DimensionSeriesValueValue basisSource
Total under constructionGW78ActualIEA: Global Energy Review 2026: Nuclear
2025 construction startsGW12.2ActualIEA: Global Energy Review 2026: Nuclear

Nuclear capacity under construction: full data table

SOURCEIEA: Global Energy Review 2026: Nuclear
VALUE BASISActual
LAST VERIFIEDSep 10, 2026
How this is calculated

Chapter 02 · Question answered

Commercial SMR capacity actually under construction.

Small modular reactors: announcements vs concrete

SMR reality check

SMR reality check

Commercial SMR capacity actually under construction worldwide, MW.

View data & sources →

SMR reality check

Rendering the interactive chart…

Expand data table
Download CSV
Small modular reactors: announcements vs concrete: data table
DimensionSeriesValueValue basisSource
China (commercial SMR)MW under construction125ActualIAEA: Nuclear Technology Review 2025
Russia (commercial SMR)MW under construction300ActualIAEA: Nuclear Technology Review 2025

Small modular reactors: announcements vs concrete: full data table

SOURCEIAEA: Nuclear Technology Review 2025
VALUE BASISActual
LAST VERIFIEDSep 10, 2026
How this is calculated
All data for this index

Data table

Download CSV
Nuclear Construction & the SMR Reality Check: full data table
GwSeriesMeasureSourceValue basisMwProject
78under_constructionTotal under constructionIEA: Global Energy Review 2026: NuclearActualNot publishedNot published
12.2under_construction2025 construction startsIEA: Global Energy Review 2026: NuclearActualNot publishedNot published
Not publishedsmr_realityNot publishedIAEA: Nuclear Technology Review 2025Actual125China (commercial SMR)
Not publishedsmr_realityNot publishedIAEA: Nuclear Technology Review 2025Actual300Russia (commercial SMR)

Method

How this evidence was built

What it measures

Counts capacity where construction has formally started: first structural concrete poured, not announcements, letters of intent, site options or memoranda. That distinction is the entire point of this index: SMR press activity is enormous and SMR construction is almost nil.

Key context

  • Just two commercial SMRs are under construction anywhere: 125 MW in China and 300 MW in Russia.
  • Note the unit change, the SMR chart is in megawatts while the capacity chart is in gigawatts, because plotting them on one axis would render the SMR bars invisible.
  • Combined, those two projects are 0.425 GW against 78 GW total under construction.
  • Context: half of all capacity under construction is in China, which expects ~100 GW installed by around 2030.
  • Egypt, India and Türkiye each have roughly 5 GW under way.

Key numbers

  • 78 GW under construction across 15 countries (iea-ger-2026-nuclear).
  • Ten construction starts totalling 12.2 GW in 2025; nine in China, one in Russia (iaea-ntr-2025).
  • Only two commercial SMRs under construction worldwide: 125 MW in China, 300 MW in Russia (iaea-ntr-2025).
  • Iaea projects SMRs at 24% of new capacity by 2050 in its high case, 5% in its low case (iaea-projections).

Caveats

Caveat: the iaea projects SMRs at 24% of new capacity by 2050 in its high case and 5% in its low case. That is an unusually wide spread and reflects how little has actually been built, not disagreement about demand. Those projections are not seeded here: they are scenario outputs, not measurements.

Do not use this to

  • Completion dates, cost, or schedule performance.
  • Announced or planned SMRs, this counts construction only.
  • Operating fleet capacity or retirements.

Scope

2025

Sources

Last verified 10 Sept 2026