Energy
The largest backlog in thirty years, and exactly two SMRs under construction
78 GW of nuclear capacity is under construction across 15 countries, one of the largest backlogs in thirty years, with ten construction starts totalling 12.2 GW in 2025, nine of them in China.
Against that, just two commercial small modular reactors are actually under construction anywhere: a 125 MW unit in China and a 300 MW unit in Russia.
Nuclear Construction & the SMR Reality Check
- 2025
- Government / regulator
- 4
- 3
- 4 actual
This page can answer
Two series: nuclear capacity under construction, and commercial SMR capacity actually being built.
It cannot answer
- Completion dates, cost, or schedule performance.
- Announced or planned SMRs, this counts construction only.
- Operating fleet capacity or retirements.
Nuclear capacity being built worldwide.
Nuclear capacity under construction
Under construction
Reactor capacity being built worldwide, GW.
Under construction
Rendering the interactive chart…
Expand data table
| Dimension | Series | Value | Value basis | Source |
|---|---|---|---|---|
| Total under construction | GW | 78 | Actual | IEA: Global Energy Review 2026: Nuclear |
| 2025 construction starts | GW | 12.2 | Actual | IEA: Global Energy Review 2026: Nuclear |
Commercial SMR capacity actually under construction.
Small modular reactors: announcements vs concrete
SMR reality check
Commercial SMR capacity actually under construction worldwide, MW.
SMR reality check
Rendering the interactive chart…
Expand data table
| Dimension | Series | Value | Value basis | Source |
|---|---|---|---|---|
| China (commercial SMR) | MW under construction | 125 | Actual | IAEA: Nuclear Technology Review 2025 |
| Russia (commercial SMR) | MW under construction | 300 | Actual | IAEA: Nuclear Technology Review 2025 |