Commercial aircraft delivered each quarter.
Deliveries have nearly doubled since the door-plug quarter
Takeaway: The 143 → 171 step in 2026 is the 737 line moving from 42 toward 47 a month.
Deliveries by quarter
Commercial aircraft delivered per quarter. Q1 2025 is omitted, not published in the releases used.
Takeaway: The 143 → 171 step in 2026 is the 737 line moving from 42 toward 47 a month.
Deliveries by quarter
The 143 → 171 step in 2026 is the 737 line moving from 42 toward 47 a month.
Rendering the interactive chart…
Expand data table
| Dimension | Series | Value | Value basis | Source |
|---|---|---|---|---|
| Q2 2024 | Aircraft delivered | 92 | Actual | Boeing: Second Quarter 2025 results |
| Q2 2025 | Aircraft delivered | 150 | Actual | Boeing: Second Quarter 2025 results |
| Q3 2025 | Aircraft delivered | 160 | Actual | Boeing: Third Quarter 2025 results, 29 October 2025 |
| Q4 2025 | Aircraft delivered | 160 | Actual | Boeing: Fourth Quarter 2025 deliveries |
| Q1 2026 | Aircraft delivered | 143 | Actual | Boeing: First Quarter 2026 results |
| Q2 2026 | Aircraft delivered | 171 | Actual | Boeing: Second Quarter 2026 results, 28 July 2026 |
Caveat: Q1 2025 is omitted, not published in the releases used and not derivable on the same basis. Not interpolated.
Data table
Download CSV| Series | Quarter | Aircraft | Source | Value basis |
|---|---|---|---|---|
| quarterly_deliveries | Q2 2024 | 92 | Boeing: Second Quarter 2025 results | Actual |
| quarterly_deliveries | Q2 2025 | 150 | Boeing: Second Quarter 2025 results | Actual |
| quarterly_deliveries | Q3 2025 | 160 | Boeing: Third Quarter 2025 results, 29 October 2025 | Actual |
| quarterly_deliveries | Q4 2025 | 160 | Boeing: Fourth Quarter 2025 deliveries | Actual |
| quarterly_deliveries | Q1 2026 | 143 | Boeing: First Quarter 2026 results | Actual |
| quarterly_deliveries | Q2 2026 | 171 | Boeing: Second Quarter 2026 results, 28 July 2026 | Actual |
How this evidence was built
What it measures
This index answers one question: is Boeing’s recovery real, and where is it still not? It is built entirely from Boeing’s own quarterly releases plus one external source for the FAA rate-cap dates, and it deliberately contains no Airbus comparison, that is /data/narrowbody-deliveries.
How it is calculated
- Derived point: disclosed.
- Q1 2025 free cash flow of $(2.3)bn is the only derived value in this index.
- The full-year 2025 release returned a Global Services operating margin that cannot be reconciled with the 18.1% quarterly figures on either side of it or with the segment’s history.
Key context
- Basis. All cash-flow figures are free cash flow as Boeing defines it (non-gaap: operating cash flow less capital expenditure).
- All margins are segment operating margin as reported.
- Backlog is total company backlog, not Commercial Airplanes alone.
- Deliveries are commercial aircraft only; Defense deliveries are excluded throughout.
- It is H1 2025 free cash flow of $(2.5)bn less the Q2 2025 figure of $(0.2)bn, both published in the same release.
- Cross-check: the Q3 2025 release gives nine-month free cash flow of $(2.252)bn, which less the Q3 figure of +$238m returns H1 of $(2.490)bn: consistent with the stated $(2.5)bn to rounding.
- The derivation is written into the point’s basis label.
- Omitted. Q1 2025 deliveries are not stated in the releases retrieved and are not derivable from a published nine-month total on the same basis.
- The quarter is absent from the delivery chart rather than interpolated.
- Conflict: dropped, not seeded.
- It is treated as unreliable.
- Full-year segment margins are therefore omitted from this index entirely; only the two 2026 quarters, which are mutually consistent, are charted.
- Compiled and verified 2026-08-14.
Key numbers
- Quarterly free cash flow: $(4,300)m in Q2 2024 → $631m in Q2 2026, but with a $(1,500)m relapse in Q1 2026, the turn is seasonal, not monotonic (boeing-q2-2025 / boeing-q2-2026 / boeing-q1-2026).
- Full-year 2025 free cash flow was still $(1.9)bn, against $(14.3)bn in 2024. The annual number has not yet crossed zero (boeing-q4-2025).
- Deliveries rose from 92 in Q2 2024 to 171 in Q2 2026: +86%, and the strongest quarter in the series (boeing-q2-2025 / boeing-q2-2026).
- Backlog grew $96bn in four quarters to a record $715.3bn, of which Commercial Airplanes is $596.7bn (boeing-q2-2025 / boeing-q2-2026).
Caveats
Caveat: 52 A month is A target. The final bar of the rate-path chart is a stated next step with no published FAA approval and no announced date. It is labelled as a target in the subtitle and in the point’s basis label. The 38 and 42 figures are regulatory caps; the 42 and 47 figures are production rates Boeing reported. Caps and rates are not the same measure and the chart’s x-axis labels say which is which.
Caveat: Production rate is not delivery rate. Boeing has been drawing down parked inventory over this period, so quarterly deliveries have at times exceeded the production rate. Do not read the rate chart as a delivery forecast.
Caveat: Seasonality. Boeing consumes cash in Q1 and generates it later in the year. The Q1 2026 outflow of $(1.5)bn is a seasonal pattern visible in 2025 as well, not necessarily a relapse. Equally, the positive quarters do not mean the annual figure has turned: full-year 2025 free cash flow was still $(1.9)bn against $(14.3)bn in 2024.
Do not use this to
- Q1 2025 deliveries, not published in the releases used and deliberately not interpolated.
- Full-year segment operating margins, the FY2025 Global Services figure did not reconcile and all full-year segment margins were dropped.
- Whether or when the FAA will approve 52 a month. No date has been published.
- Revenue or margin per aircraft. Deliveries and segment revenue are given, but Boeing does not publish per-unit economics.
Scope
July 2026
Sources
Last verified 10 Sept 2026