Can the single-aisle duopoly build what it has already sold?

Airbus and Boeing carry 12,999 unbuilt single-aisle aircraft between them, about four fifths of a combined 16,136-aircraft backlog, or roughly a decade of production at 2025 rates.

Both have announced rates neither has ever achieved: Airbus 75 A320-family aircraft a month by end-2027 against a 2025 average of 50.6, Boeing 52 a month against 37.3 and with no published FAA approval for the step. The constraint appears to be shifting: LEAP engine deliveries grew 41% in H1 2026, well ahead of airframe output, which moves the bottleneck back onto final assembly.

Narrowbody Deliveries: Can the Duopoly Build What It Sold?

Data date
July 2026
Source class
Official body or company filing
Data points
18
Sources
16
Value basis
18 actual

Caveat: The 34 remaining 737 NG orders are a pre-MAX residue, shown rather than dropped because they are still contractual.

This page can answer

Six series on single-aisle capacity: unfilled orders by programme at 31 July 2026, the month-on-month backlog shift, announced end-state monthly rates, the 2026 year-to-date delivery and order scorecard, June 2026 output split by body type, and GE Aerospace LEAP growth rates.

It cannot answer

  • Absolute LEAP or GTF unit deliveries: GE publishes growth percentages only and Pratt & Whitney publishes no comparable figure.
  • A320-family or 737 deliveries per year as separate annual series, no primary per-family annual table was sourced in this pass.
  • Whether either OEM will reach its announced rate, or when. The targets carry dates; the dates are management statements, not commitments.
Jump to chaptersSource ledger
Evidence chapters

Chapter 01 · Question answered

How many single-aisle aircraft are sold and unbuilt, by programme.

The single-aisle duopoly has sold a decade of production it has not built

Single-aisle backlog

Single-aisle backlog

Unfilled single-aisle orders at 31 July 2026, aircraft. Airbus total backlog 9,352; Boeing 6,784.

View data & sources →

Single-aisle backlog

Rendering the interactive chart…

Expand data table
Download CSV
The single-aisle duopoly has sold a decade of production it has not built: data table
DimensionSeriesValueValue basisSource
A320neo familyAircraft on order7574ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
737 MAXAircraft on order4817ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
A220Aircraft on order574ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
737 NGAircraft on order34ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries

The single-aisle duopoly has sold a decade of production it has not built: full data table

SOURCEForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: The 34 remaining 737 ng orders are a pre-max residue, shown rather than dropped because they are still contractual.

How this is calculated

Chapter 02 · Question answered

Which way each single-aisle backlog moved between end-June and end-July 2026.

In one month Airbus’s queue grew and Boeing’s shrank

Backlog month on month

Backlog month on month

Single-aisle backlog at end-June against end-July 2026, aircraft. Boeing figure combines MAX and NG on both dates.

View data & sources →

Backlog month on month

Rendering the interactive chart…

Expand data table
Download CSV

In one month Airbus’s queue grew and Boeing’s shrank: full data table

SOURCEForecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveries
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: One month is not a trend, and July is an order-announcement-heavy month. The Boeing July value is max 4,817 + ng 34 = 4,851, summed so both months sit on the same basis as the June combined line.

How this is calculated

Chapter 03 · Question answered

What monthly rate each single-aisle programme has publicly committed to.

Both OEMs are promising rates neither has ever achieved

Announced rate targets

Announced rate targets

Announced end-state monthly production rate by single-aisle programme. All three are stated targets, not approved or achieved rates.

View data & sources →

Announced rate targets

Rendering the interactive chart…

Expand data table
Download CSV
Both OEMs are promising rates neither has ever achieved: data table
DimensionSeriesValueValue basisSource
A320 familyAircraft per month (target)75ActualAirbus: Half-Year 2026 results, 29 July 2026
737 MAXAircraft per month (target)52ActualBoeing: Second Quarter 2026 results, 28 July 2026
A220Aircraft per month (target)13ActualAirbus: Half-Year 2026 results, 29 July 2026

Both OEMs are promising rates neither has ever achieved: full data table

SOURCEAirbus: Half-Year 2026 results, 29 July 2026 · Boeing: Second Quarter 2026 results, 28 July 2026
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Targets, not achieved or approved rates. Boeing’s 52 has no published FAA approval and no timetable.

How this is calculated

Chapter 04 · Question answered

Deliveries and gross orders for each OEM, January to July 2026.

Airbus is winning orders more than twice as fast as it is winning deliveries

2026 YTD scorecard

2026 YTD scorecard

Commercial aircraft delivered and gross orders booked, 1 January to 31 July 2026.

View data & sources →

2026 YTD scorecard

Rendering the interactive chart…

Expand data table
Download CSV
Airbus is winning orders more than twice as fast as it is winning deliveries: data table
DimensionSeriesValueValue basisSource
AirbusDeliveries YTD418ActualAirbus: Orders & Deliveries, July 2026
AirbusGross orders YTD1090ActualAirbus: Orders & Deliveries, July 2026
BoeingDeliveries YTD367ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
BoeingGross orders YTD483ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries

Airbus is winning orders more than twice as fast as it is winning deliveries: full data table

SOURCEAirbus: Orders & Deliveries, July 2026 · Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Gross orders, not net: cancellations are not deducted.

How this is calculated

Chapter 05 · Question answered

What share of each OEM’s monthly output is single-aisle.

Airbus is a narrowbody company; Boeing is not

Output mix by body type

Output mix by body type

June 2026 deliveries split by body type, aircraft.

View data & sources →

Output mix by body type

Rendering the interactive chart…

Expand data table
Download CSV

Airbus is a narrowbody company; Boeing is not: full data table

SOURCEForecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveries
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: A single month, chosen because it is the most recent with a published body-type split.

How this is calculated

Chapter 06 · Question answered

How fast LEAP engine output is growing.

The engine makers are ramping faster than the airframers

Engine throughput

Engine throughput

GE Aerospace growth rates, 2026. LEAP powers every 737 MAX and roughly half of A320neo deliveries. Percentages, not unit counts: GE does not publish absolute LEAP deliveries.

View data & sources →

Engine throughput

Rendering the interactive chart…

Expand data table
Download CSV
The engine makers are ramping faster than the airframers: data table
DimensionSeriesValueValue basisSource
LEAP deliveries, H1 2026Year-on-year growth (%)41ActualGE Aerospace: Second Quarter 2026 results, 16 July 2026
LEAP units, Q2 2026Year-on-year growth (%)24ActualGE Aerospace: Second Quarter 2026 results, 16 July 2026
Total unit volume, Q2 2026Year-on-year growth (%)26ActualGE Aerospace: Second Quarter 2026 results, 16 July 2026
CES equipment revenue, Q2 2026Year-on-year growth (%)30ActualGE Aerospace: Second Quarter 2026 results, 16 July 2026

The engine makers are ramping faster than the airframers: full data table

SOURCEGE Aerospace: Second Quarter 2026 results, 16 July 2026
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Percentages only: ge does not publish absolute leap unit counts, so the base is unknown. Pratt & Whitney gtf is omitted for lack of a citable primary figure, so this measures one of the two engine families.

How this is calculated
All data for this index

Data table

Download CSV
Narrowbody Deliveries: Can the Duopoly Build What It Sold?: full data table
SeriesAircraftProgrammeSourceValue basisJul 2026Jun 2026Rate per monthOemDeliveriesGross ordersWidebodyNarrowbodyPctMetric
sa_backlog7574A320neo familyForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
sa_backlog4817737 MAXForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
sa_backlog574A220Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
sa_backlog34737 NGForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
backlog_shiftNot publishedA320neo familyForecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveriesActual75747461Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
backlog_shiftNot published737 (MAX + NG)Forecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveriesActual48514888Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
backlog_shiftNot publishedA220Forecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveriesActual574581Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
rate_targetsNot publishedA320 familyAirbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot published75Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
rate_targetsNot published737 MAXBoeing: Second Quarter 2026 results, 28 July 2026EstimateNot publishedNot published52Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
rate_targetsNot publishedA220Airbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot published13Not publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published
ytd_scorecardNot publishedNot publishedAirbus: Orders & Deliveries, July 2026ActualNot publishedNot publishedNot publishedAirbus4181090Not publishedNot publishedNot publishedNot published
ytd_scorecardNot publishedNot publishedForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedNot publishedNot publishedBoeing367483Not publishedNot publishedNot publishedNot published
output_mixNot publishedNot publishedForecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveriesActualNot publishedNot publishedNot publishedAirbusNot publishedNot published782Not publishedNot published
output_mixNot publishedNot publishedForecast International Flight Plan: Airbus and Boeing June 2026 orders and deliveriesActualNot publishedNot publishedNot publishedBoeingNot publishedNot published2143Not publishedNot published
engine_throughputNot publishedNot publishedGE Aerospace: Second Quarter 2026 results, 16 July 2026ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published41LEAP deliveries, H1 2026
engine_throughputNot publishedNot publishedGE Aerospace: Second Quarter 2026 results, 16 July 2026ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published24LEAP units, Q2 2026
engine_throughputNot publishedNot publishedGE Aerospace: Second Quarter 2026 results, 16 July 2026ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published26Total unit volume, Q2 2026
engine_throughputNot publishedNot publishedGE Aerospace: Second Quarter 2026 results, 16 July 2026ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot publishedNot published30CES equipment revenue, Q2 2026

Method

How this evidence was built

What it measures

This index answers one question: the single-aisle duopoly has sold roughly a decade of production it has not built: can it build it? Every chart isolates one input to that answer: how deep the queue is, which way it is moving, what rates have been announced against it, what is actually coming off the lines, and whether the engine makers are keeping up.

How it is calculated

  1. The July value in the month-on-month chart is the sum, 4,851, so both months sit on the same basis.

Key context

  • Scope. Single-aisle programmes only: A320neo family, A220, 737 max and the residual 737 ng book.
  • Twin-aisle figures appear only where they are needed as a denominator (the June output-mix chart).
  • Basis: backlog comparison.
  • The June source reports the Boeing 737 backlog as one combined line (4,888); the July source splits it into max (4,817) and ng (34).
  • That addition is stated in the basis label of the point.
  • It is arithmetic on two published figures, not an estimate.
  • Source tiers. Company primary disclosure (Airbus, Boeing, ge Aerospace) is used wherever the figure exists there.
  • Monthly backlog splits are not published in that form by either oem and come from a trade compilation; the Boeing year-to-date figure from that compilation reconciles exactly against Boeing’s own quarterly releases (143 + 171 + 53 = 367), which is the corroboration standard applied.
  • Supersedes. This index absorbs and extends the three H1-2026 sections of /data/airbus-vs-boeing, which remains live so no url is lost.
  • Compiled and verified 2026-08-14.

Key numbers

  • Single-aisle backlog at 31 July 2026: A320neo family 7,574, 737 max 4,817, A220 574, 737 ng 34. 12,999 aircraft, ~81% of the two OEMs’ combined book (fi-jul-2026).
  • In July 2026 the A320neo backlog grew 113 aircraft while the 737 backlog fell 37, the books are diverging faster than the output is (fi-jun-2026 / fi-jul-2026).
  • Announced targets vs 2025 realised monthly averages: A320 family 75 vs 50.6 (+48%), 737 52 vs 37.3 (+40%), A220 13 vs 7.8 (+67%). No single-aisle programme at either company has run at its own target rate (airbus-h1-2026 / boeing-q2-2026).
  • YTD through July 2026: Airbus 418 deliveries and 1,090 gross orders; Boeing 367 and 483. The delivery gap is 14%, the order gap is a factor of 2.3 (airbus-od-jul26 / fi-jul-2026).

Caveats

Caveat: Targets are not rates. Every value in the rate-target chart is a stated management target with a future date, not an approved or achieved rate. Airbus has announced 70-75 A320-family aircraft a month by end-2027 and 13 A220s a month in 2028. Boeing has named 52 a month as the step beyond the 47 it began transitioning to in Q2 2026, with no published FAA approval and no timetable. For scale, the 2025 realised monthly averages were 50.6 (A320 family), 37.3 (737) and 7.8 (A220). No single-aisle programme at either company has ever run at its own stated target rate.

Caveat: Engines, one family only. Ge Aerospace publishes leap delivery growth percentages and does not publish absolute leap unit counts, so the engine chart is in percent and the base is unknown. Pratt & Whitney gtf delivery counts, which cover the other half of the A320neo book, were sought and not found in a citable primary release; they are omitted rather than estimated. Read that chart as evidence about one engine family, not about total narrowbody engine supply.

Caveat: One month is not A trend. The June-to-July backlog movement and the June output-mix split are single-month observations. July is an order-announcement-heavy month in this industry. They are shown because they are cleanly sourced and directional, not because one month establishes a rate.

Do not use this to

  • Absolute leap or gtf unit deliveries: ge publishes growth percentages only and Pratt & Whitney publishes no comparable figure.
  • A320-family or 737 deliveries per year as separate annual series, no primary per-family annual table was sourced in this pass.
  • Whether either oem will reach its announced rate, or when. The targets carry dates; the dates are management statements, not commitments.
  • Net orders. Only gross orders are charted; cancellations are not deducted.