452 aircraft in five months, the arithmetic behind Airbus’s 2026 guidance

Airbus delivered 418 aircraft in the seven months to 31 July 2026 and guides to about 870 for the year.

That leaves 452 in five months, an average of 90.4 a month: against a best-ever completed August-to-December finish of 420 in 2025. Airbus has never delivered 870 in a year; its record is 863, set in 2019. The same 452 aircraft also have to close a free-cash-flow gap: H1 2026 consumed €1.166bn against full-year guidance of about €4.5bn, so roughly €5.7bn of inflow depends on them.

Airbus: 452 Aircraft in Five Months

Data date
July 2026
Source class
Official body or company filing
Data points
29
Sources
16
Value basis
29 actual

Caveat: 2026 is deliberately EXCLUDED, the year is incomplete and its 870 figure is guidance, not an actual.

This page can answer

Seven series: annual deliveries 2019–2025, the 2026 delivery arithmetic, December deliveries by year, H1 2026 deliveries by family, announced programme rate targets, backlog by family at 31 July 2026, and H1 2026 headline financials.

It cannot answer

  • February, March and April 2026 monthly deliveries, not sourced in this pass, so no monthly 2026 series is charted.
  • Whether Airbus will meet the ~870 guidance. This index gives the arithmetic and the historical base rate, not a forecast.
  • Order intake by family for 2026, or net orders. Only deliveries and backlog are charted here.
Jump to chaptersSource ledger
Evidence chapters

Chapter 01 · Question answered

How many commercial aircraft Airbus delivered each year.

Airbus has not beaten its 2019 delivery record in seven years

Annual deliveries

Annual deliveries

Commercial aircraft delivered per calendar year. 2026 is excluded, the year is incomplete and its 870 figure is guidance, not an actual.

View data & sources →

Annual deliveries

Rendering the interactive chart…

Expand data table
Download CSV

Airbus has not beaten its 2019 delivery record in seven years: full data table

SOURCEAirbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023) · Airbus: 793 commercial aircraft deliveries in 2025
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: 2026 is deliberately excluded, the year is incomplete and its 870 figure is guidance, not an actual.

How this is calculated

Chapter 02 · Question answered

What Airbus has delivered, what remains, and what it has actually managed before.

452 aircraft in five months, against a best-ever five-month finish of 420

The 2026 arithmetic

The 2026 arithmetic

The 2026 delivery arithmetic, aircraft. The 452 figure is the remainder against a guidance target of about 870, not an actual.

View data & sources →

The 2026 arithmetic

Rendering the interactive chart…

Expand data table
Download CSV
452 aircraft in five months, against a best-ever five-month finish of 420: data table
DimensionSeriesValueValue basisSource
Delivered Jan–Jul 2026Aircraft418ActualAirbus: Orders & Deliveries, July 2026
Remaining to reach 870 guidanceAircraft452ActualAirways Magazine: Airbus has five months to deliver another 452 aircraft
Actually delivered Aug–Dec 2025Aircraft420ActualAirways Magazine: Airbus has five months to deliver another 452 aircraft

452 aircraft in five months, against a best-ever five-month finish of 420: full data table

SOURCEAirbus: Orders & Deliveries, July 2026 · Airways Magazine: Airbus has five months to deliver another 452 aircraft
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: The 452 bar is a remainder against guidance of ~870, not an actual. Guidance carries a practical range of ~850–890, so the low end implies ~432.

How this is calculated

Chapter 03 · Question answered

How large Airbus’s year-end delivery push has been.

Airbus finishes years in a sprint, and 2026 needs five of them in a row

December surge

December surge

December deliveries by year, aircraft. Required monthly average for August–December 2026: 90.4.

View data & sources →

December surge

Rendering the interactive chart…

Expand data table
Download CSV
Airbus finishes years in a sprint, and 2026 needs five of them in a row: data table
DimensionSeriesValueValue basisSource
2023December deliveries112ActualAirways Magazine: Airbus has five months to deliver another 452 aircraft
2024December deliveries123ActualAirways Magazine: Airbus has five months to deliver another 452 aircraft
2025December deliveries136ActualAirways Magazine: Airbus has five months to deliver another 452 aircraft

Airbus finishes years in a sprint, and 2026 needs five of them in a row: full data table

SOURCEAirways Magazine: Airbus has five months to deliver another 452 aircraft
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Structural, not anomalous: revenue is recognised on handover and both parties concentrate handovers at year end.

How this is calculated

Chapter 04 · Question answered

Which product lines delivered the first half’s 351 aircraft.

Seventy-seven per cent of the ramp is one aircraft family

H1 2026 by family

H1 2026 by family

H1 2026 deliveries by product family, aircraft. Total 351.

View data & sources →

H1 2026 by family

Rendering the interactive chart…

Expand data table
Download CSV
Seventy-seven per cent of the ramp is one aircraft family: data table
DimensionSeriesValueValue basisSource
A320 FamilyAircraft delivered271ActualAirbus: Half-Year 2026 results, 29 July 2026
A220Aircraft delivered44ActualAirbus: Half-Year 2026 results, 29 July 2026
A350Aircraft delivered26ActualAirbus: Half-Year 2026 results, 29 July 2026
A330Aircraft delivered10ActualAirbus: Half-Year 2026 results, 29 July 2026

Seventy-seven per cent of the ramp is one aircraft family: full data table

SOURCEAirbus: Half-Year 2026 results, 29 July 2026
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Sums to 351, reconciling against the H1 headline.

How this is calculated

Chapter 05 · Question answered

The monthly rate each Airbus programme is targeting, and when.

Every Airbus rate target now sits in 2027 or later

Programme rate targets

Programme rate targets

Announced target monthly production rate by programme, with the target year. All four are stated targets, not achieved rates.

View data & sources →

Programme rate targets

Rendering the interactive chart…

Expand data table
Download CSV
Every Airbus rate target now sits in 2027 or later: data table
DimensionSeriesValueValue basisSource
A320 Family (2027)Aircraft per month (target)75ActualAirbus: Half-Year 2026 results, 29 July 2026
A220 (2028)Aircraft per month (target)13ActualAirbus: Half-Year 2026 results, 29 July 2026
A350 (2028)Aircraft per month (target)12ActualAirbus: Half-Year 2026 results, 29 July 2026
A330 (2029)Aircraft per month (target)5ActualAirbus: Half-Year 2026 results, 29 July 2026

Every Airbus rate target now sits in 2027 or later: full data table

SOURCEAirbus: Half-Year 2026 results, 29 July 2026
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Targets, not achieved rates. Not one target date falls inside the current guidance year.

How this is calculated

Chapter 06 · Question answered

Unfilled Airbus orders by product family.

A twelve-and-a-half-year queue on one product line

Backlog by family

Backlog by family

Airbus unfilled orders by family at 31 July 2026, aircraft. Total 9,352.

View data & sources →

Backlog by family

Rendering the interactive chart…

Expand data table
Download CSV
A twelve-and-a-half-year queue on one product line: data table
DimensionSeriesValueValue basisSource
A320neo familyAircraft on order7574ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
A350Aircraft on order870ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
A220Aircraft on order574ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
A330Aircraft on order334ActualForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries

A twelve-and-a-half-year queue on one product line: full data table

SOURCEForecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveries
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: Sums to 9,352. Airbus’s own cumulative table implies 9,358 on a slightly different cut-off, a 0.06% gap, disclosed.

How this is calculated

Chapter 07 · Question answered

Airbus revenue, profit, net cash and free cash flow for the first half.

Record profit, negative cash, and €5.7bn of free cash flow still to find

H1 2026 financials

H1 2026 financials

Airbus H1 2026, € billions. Full-year guidance: EBIT Adjusted about €7.5bn and free cash flow about €4.5bn.

View data & sources →

H1 2026 financials

Rendering the interactive chart…

Expand data table
Download CSV
Record profit, negative cash, and €5.7bn of free cash flow still to find: data table
DimensionSeriesValueValue basisSource
Revenues€ bn33.2ActualAirbus: Half-Year 2026 results, 29 July 2026
EBIT Adjusted€ bn2.727ActualAirbus: Half-Year 2026 results, 29 July 2026
Net cash position€ bn8.36ActualAirbus: Half-Year 2026 results, 29 July 2026
Free cash flow before customer financing€ bn-1.166ActualAirbus: Half-Year 2026 results, 29 July 2026

Record profit, negative cash, and €5.7bn of free cash flow still to find: full data table

SOURCEAirbus: Half-Year 2026 results, 29 July 2026
VALUE BASISActual
LAST VERIFIEDSep 10, 2026

Caveat: EBIT Adjusted is Airbus’s own alternative performance measure; free cash flow is before customer financing.

How this is calculated
All data for this index

Data table

Download CSV
Airbus: 452 Aircraft in Five Months: full data table
YearSeriesAircraftSourceValue basisItemFamilyProgrammeRate per monthEur bnMetric
2019annual_deliveries863Airbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023)ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2020annual_deliveries566Airbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023)ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2021annual_deliveries611Airbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023)ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2022annual_deliveries661Airbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023)ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2023annual_deliveries735Airbus: 2023 commercial aircraft orders & deliveries infographic (annual history 2019–2023)ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2024annual_deliveries766Airbus: 793 commercial aircraft deliveries in 2025ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2025annual_deliveries793Airbus: 793 commercial aircraft deliveries in 2025ActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
Not publishedytd_vs_target418Airbus: Orders & Deliveries, July 2026ActualDelivered Jan–Jul 2026Not publishedNot publishedNot publishedNot publishedNot published
Not publishedytd_vs_target452Airways Magazine: Airbus has five months to deliver another 452 aircraftActualRemaining to reach 870 guidanceNot publishedNot publishedNot publishedNot publishedNot published
Not publishedytd_vs_target420Airways Magazine: Airbus has five months to deliver another 452 aircraftActualActually delivered Aug–Dec 2025Not publishedNot publishedNot publishedNot publishedNot published
2023december_surge112Airways Magazine: Airbus has five months to deliver another 452 aircraftActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2024december_surge123Airways Magazine: Airbus has five months to deliver another 452 aircraftActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
2025december_surge136Airways Magazine: Airbus has five months to deliver another 452 aircraftActualNot publishedNot publishedNot publishedNot publishedNot publishedNot published
Not publishedh1_by_family271Airbus: Half-Year 2026 results, 29 July 2026ActualNot publishedA320 FamilyNot publishedNot publishedNot publishedNot published
Not publishedh1_by_family44Airbus: Half-Year 2026 results, 29 July 2026ActualNot publishedA220Not publishedNot publishedNot publishedNot published
Not publishedh1_by_family26Airbus: Half-Year 2026 results, 29 July 2026ActualNot publishedA350Not publishedNot publishedNot publishedNot published
Not publishedh1_by_family10Airbus: Half-Year 2026 results, 29 July 2026ActualNot publishedA330Not publishedNot publishedNot publishedNot published
Not publishedrate_targetsNot publishedAirbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot publishedA320 Family (2027)75Not publishedNot published
Not publishedrate_targetsNot publishedAirbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot publishedA220 (2028)13Not publishedNot published
Not publishedrate_targetsNot publishedAirbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot publishedA350 (2028)12Not publishedNot published
Not publishedrate_targetsNot publishedAirbus: Half-Year 2026 results, 29 July 2026EstimateNot publishedNot publishedA330 (2029)5Not publishedNot published
Not publishedbacklog_by_family7574Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedA320neo familyNot publishedNot publishedNot publishedNot published
Not publishedbacklog_by_family870Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedA350Not publishedNot publishedNot publishedNot published
Not publishedbacklog_by_family574Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedA220Not publishedNot publishedNot publishedNot published
Not publishedbacklog_by_family334Forecast International Flight Plan: Airbus and Boeing July 2026 orders and deliveriesActualNot publishedA330Not publishedNot publishedNot publishedNot published
Not publishedh1_financialsNot publishedAirbus: Half-Year 2026 results, 29 July 2026ActualNot publishedNot publishedNot publishedNot published33.2Revenues
Not publishedh1_financialsNot publishedAirbus: Half-Year 2026 results, 29 July 2026ActualNot publishedNot publishedNot publishedNot published2.727EBIT Adjusted
Not publishedh1_financialsNot publishedAirbus: Half-Year 2026 results, 29 July 2026ActualNot publishedNot publishedNot publishedNot published8.36Net cash position
Not publishedh1_financialsNot publishedAirbus: Half-Year 2026 results, 29 July 2026ActualNot publishedNot publishedNot publishedNot published-1.166Free cash flow before customer financing

Method

How this evidence was built

What it measures

This index answers one question: Airbus guides to about 870 deliveries in 2026 and had delivered 418 by 31 July. Can it deliver the remaining 452 in five months? Every chart is an input to that arithmetic, the company’s historical annual pace, its year-end surge behaviour, which product lines the ramp actually runs through, what rates have been announced, how deep the queue is, and what the cash position implies. It contains no Boeing comparison; that is /data/narrowbody-deliveries.

Key context

  • Basis. Deliveries are commercial aircraft handed over to customers, the basis Airbus uses in its monthly Orders & Deliveries report.
  • Helicopters and Defence & Space are excluded throughout.
  • Financials are as reported in the H1 2026 release: EBIT Adjusted is Airbus’s own alternative performance measure and free cash flow is before customer financing.
  • Compiled and verified 2026-08-14.

Key numbers

  • Airbus delivered 863 aircraft in 2019 and has not beaten it since: 566, 611, 661, 735, 766, 793. The 2026 guidance of ~870 would be an all-time high (airbus-infographic-2023 / airbus-fy2025).
  • 418 delivered through July 2026 leaves 452 in five months. 90.4 a month, against a best completed Aug–Dec finish of 420 (airbus-od-jul26 / airways-452).
  • December deliveries: 112 (2023), 123 (2024), 136 (2025). Only December 2024 and 2025 have ever exceeded the pace 2026 now needs for five consecutive months (airways-452).
  • 271 of 351 H1 2026 deliveries were A320-family: 77% of the ramp runs through one product line (airbus-h1-2026).

Caveats

Caveat: Guidance is not an actual. The 452 bar is a remainder computed against a guidance figure of about 870, and the guidance carries a practical range of roughly 850-890. At the low end the requirement falls to about 432: still above Airbus’s best completed August-to-December finish of 420. The 2026 year is deliberately excluded from the annual delivery series so that no forecast sits in a chart of actuals.

Caveat: Rate targets are targets. Every value in the rate chart is a stated management target with a future date: A320 family 70-75 a month by end-2027, A220 rate 13 in 2028, A350 rate 12 in 2028, A330 rate 5 in 2029. For scale, the realised 2025 monthly averages were 50.6, 7.8, 4.8 and 3.0 respectively. Not one target date falls inside the current guidance year, so none of them affects the 2026 number.

Caveat: Backlog measurement gap, disclosed. The per-family backlog figures sum to 9,352 at 31 July 2026. Airbus’s own cumulative orders and deliveries table implies 9,358 at the same point, a six-aircraft difference arising from slightly different cut-off conventions. Six aircraft on 9,352 is 0.06% and changes nothing here; it is disclosed because a source that hides small discrepancies should not be trusted with large ones.

Do not use this to

  • February, March and April 2026 monthly deliveries, not sourced in this pass, so no monthly 2026 series is charted.
  • Whether Airbus will meet the ~870 guidance. This index gives the arithmetic and the historical base rate, not a forecast.
  • Order intake by family for 2026, or net orders. Only deliveries and backlog are charted here.
  • Which supplier or programme constraint is binding. Airbus has not published a constraint attribution for 2026.

Scope

July 2026

Sources

Last verified 10 Sept 2026